How Do I Assign Subcontractors to Projects?
You can assign subcontractors to projects in the 'Projects' module on the system.
- On the left column, go to 'Projects'.
- Click on the project you want to assign the subcontractor to.
- Scroll down to the 'Subcontractors' section.
- Click 'Allocate/Deallocate Subcontractors'.
- Two sections will show ‘Select to Add’ and ‘Select to Remove’ with a list of subcontractors.
- Tick the box(es) you wish to add/remove.
- You also have the option to select all subcontractors, click on the blue tick at the top of the page.
- To deselect all subcontractors, click on the red ‘x’ at the top of the page.
- Click the arrow button.
- Click 'Close'.
The subcontractors you have selected will now be assigned to the project.